You are the project manager of the software installation project in the table below. You would like to find the minimum-cost
You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond wook 25. In addition, your project team determined that indirect project costs are $1,500 per week Activity Immediate Predecessors) > AB - Immo Normal Time Normal Cost Crash Time Crash Cost weeks) (5) (weeks) ($) 3,000 8.000 3,000 7.000 10,000 12,000 3.000 9,000 4,000 5,000 4,000 8,500 2,000 2,000 5,000 7.000 7,000 15.000 NOON E, F G C.F a. What would be your target completion week? The target completion week is week (Enter your response as an integer)

Expert Answer


ALL POSSIBLE PATHS: ACI = 20 BDFI = 35 ADFI = 30 ADFGH = 34 BDFGH = 39 BEGH = 23 CRITICAL PATH = B-F-G = 39 CRASHING SCHEDULE CRASH COST PER PERIOD = (CRASH COST - NORMAL C