(Solved): It Is Currently Day 26 Of A Project. BCWS, BCWP, And AC To Date Are 11m, 17m, And 9m Respectively. T ...

It is currently day 26 of a project. BCWS, BCWP, and AC to date are 11m, 17m, and 9m respectively. Then what is the SPI of the project to date?  

(Please keep two decimal points!)

Expert Answer


We have an Answer from Expert Buy This Answer $6