(Solved): The Following Table Lists The Components Needed To Assemble An End Item, Lead Times, And Quantities ...

The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (wk) Amo

The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (wk) Amount on hand End 1 0 B 3 10 C 4 D 4 25 E 2 11 F 1 26 G 2 7 H 1 0 9 End Item B (2) D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 24 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.) The latest week

Expert Answer


Answer a: 189 additional units of E are needed Explanation: Item Relation Requirement= relation *net requirement of related part Inventory net requiremen
We have an Answer from Expert Buy This Answer $6