You have been asked to evaluate a project performance using earned value management techniques. It is currently day 53 of a project. BCWS, BCWP, and AC to date are 22.6m, 24.6m, and 24.4m respectively. Then what is the CV of the project to date?  (Please keep two decimal points!)